Anderson Ave walking pathway

  • Project typeWalking path construction
  • Project value$580,000
  • Project scheduleMay 2025 - June 2025

Background

Anderson Avenue, Paxton received $580,000 under the ‘Active Transport to School - Get Active NSW’ Grant funded by Transport for NSW which will encourage children to safely walk and ride to school.

Scope of Works

The walking path at Anderson Avenue, Paxton includes:

  • 1.8m wide walking path
  • 600m in length from the corner of Middle Road and Anderson Avenue and continues to the existing footpath outside Paxton Public School
  • Handrails
  • Kerb & Gutter to complete Anderson Avenue drainage

Location

Anderson Ave footpath.png

Traffic Management

A Traffic Management Plan (TMP) will be in place for the duration of the works and Variable Message Signs (VMS) will be displayed at various locations to inform the residents and road users.

Traffic control and reduced speed limits will be in place for the duration of the works.

Residents will be notified for how this project will impact their everyday use of this road whilst construction works are ongoing.

Funding

The project budget has been entirely funded by the ‘Active Transport to School - Get Active NSW’ Grant which has been endorsed by Transport for NSW.