Kurri Kurri Netball Facility

  • Project typePark & Facility Upgrade
  • Project scheduleConstruction starting early 2025
  • Contractor nameGlascott | Landscape and Civil
Hero.png

Background

The Kurri Kurri Netball Facility Project, located within Booth Park, aims to deliver much-needed upgrades to the park’s sporting infrastructure. The project will enhance local participation in netball, benefit school groups and community organisations, and provide the capacity to host netball tournaments and events in Kurri Kurri.

In May 2021, Cessnock City Council resolved to relocate the Kurri Kurri Netball Courts from Molly Worthington Netball Facility to Booth Park to meet the future needs of netball in the Kurri Kurri Planning Area.

A draft concept plan was developed and placed on public exhibition, and a community meeting was held on 16 June 2022. During this meeting, impacted stakeholders shared concerns about road conditions, parking, traffic, noise, and stormwater drainage issues.

In 2022, as part of the Federal election, a $7.5 million funding commitment was made to Council, enabling the project to progress to detailed designs for the new facility. The concerns raised by residents during the 2022 community meeting have been noted and incorporated into the final design.


Scope of works

The Kurri Kurri Netball Facility Project will involve the following improvements:

  • 12 new plexipave surfaced netball courts
  • Floodlighting
  • A multipurpose half-court
  • A new amenities building featuring storage, canteen, changerooms, referee’s room, first aid room, meeting space, office, and toilet facilities
  • Two car parks
  • Park furniture
  • Installation of an Onsite Stormwater Detention to manage stormwater runoff
  • Landscaping

Kurri Kurri Netball Facility

Hero.png

Courts

1. Netball Courts.png

View from the Amenities block

2. View from the Amenities.png

Courts and Landscaping

3. Courts and Landscaping.png

Amenities Block and Drop off Zone

4. Amenities and drop off.png

Amenities block and seating

5. Amenities and Seating.png


Project schedule & updates

Construction works are scheduled to start on 20 January 2025, with estimated completion in December 2025.

October 2025 Update

There’s been some fantastic progress on site lately. Asphalting of all 12 courts has been completed, and the new surface looks incredible. The asphalt will now cure for 21 days, with the acrylic surface application to begin mid-November.

With the pavilion now at lock up, things have really ramped up inside. Electrical, plumbing, and air-conditioning rough-ins are underway, along with internal framing, wall sheeting, and fitting-off works. You’ll soon start to see tiles, fixtures, and finishes coming together, giving a real sense of the building’s final form.

Outside, concrete and carpark works are progressing well and beginning to tie the precinct together, creating a clear picture of how the finished facility will look.

kurri kurri netball courts_1.jpg

 

kurri kurri netball courts_2.jpg

 

kurri kurri netball courts_3.jpg

 

kurri kurri netball courts_4.jpg

Funding

This project has been made possible by funding from:

  • The Australian Government via the Priority Community Infrastructure Program ($7,500,000)
  • NSW Government via Level Playing Field Program 2023/24 ($1,898,400)
  • Developer contributions
  • Cessnock City Council Operational Budget

Location

Booth Park, Kurri Kurri 2327  View Map

Google Map