Kurri Kurri Netball Facility

  • Project typePark & Facility Upgrade
  • Project scheduleConstruction starting early 2025
  • Contractor nameGlascott | Landscape and Civil
Hero.png

Background

The Kurri Kurri Netball Facility Project, located within Booth Park, aims to deliver much-needed upgrades to the park’s sporting infrastructure. The project will enhance local participation in netball, benefit school groups and community organisations, and provide the capacity to host netball tournaments and events in Kurri Kurri.

In May 2021, Cessnock City Council resolved to relocate the Kurri Kurri Netball Courts from Molly Worthington Netball Facility to Booth Park to meet the future needs of netball in the Kurri Kurri Planning Area.

A draft concept plan was developed and placed on public exhibition, and a community meeting was held on 16 June 2022. During this meeting, impacted stakeholders shared concerns about road conditions, parking, traffic, noise, and stormwater drainage issues.

In 2022, as part of the Federal election, a $7.5 million funding commitment was made to Council, enabling the project to progress to detailed designs for the new facility. The concerns raised by residents during the 2022 community meeting have been noted and incorporated into the final design.


Scope of works

The Kurri Kurri Netball Facility Project will involve the following improvements:

  • 12 new plexipave surfaced netball courts
  • Floodlighting
  • A multipurpose half-court
  • A new amenities building featuring storage, canteen, changerooms, referee’s room, first aid room, meeting space, office, and toilet facilities
  • Two car parks
  • Park furniture
  • Installation of an Onsite Stormwater Detention to manage stormwater runoff
  • Landscaping

Kurri Kurri Netball Facility

Hero.png

Courts

1. Netball Courts.png

View from the Amenities block

2. View from the Amenities.png

Courts and Landscaping

3. Courts and Landscaping.png

Amenities Block and Drop off Zone

4. Amenities and drop off.png

Amenities block and seating

5. Amenities and Seating.png


Project schedule & updates

Construction works are scheduled to start on 20 January 2025, with estimated completion in December 2025.

November 2025 Update

There’s been some great progress on site over the past few weeks, and the facility is really starting to come together. Cooltop surfacing works have now begun, with all courts patched and primed, and the first few courts already completed. The bright new surface is giving a real sense of what the finished facility will look like.

External works are also moving along strongly. Vehicle bollards and handrails are being installed, and the carpark kerb is now in place. Landscaping has kicked off too, with the first trees planted, helping to tie the site together and soften the edges of the new infrastructure.

Inside the pavilion, we’re at the pointy end of construction. Painting is well underway, and fit-off works including tapware, electrical switches, lighting, and internal fixtures are progressing quickly. The building is looking fantastic and nearing completion.

 

KKNF-November-1.jpg

 

KKNF-November-2.jpg

 

KKNF-November-3.jpg

 

KKNF-November-4.jpg

 

KKNF-November-5.jpg

Funding

This project has been made possible by funding from:

  • The Australian Government via the Priority Community Infrastructure Program ($7,500,000)
  • NSW Government via Level Playing Field Program 2023/24 ($1,898,400)
  • Developer contributions
  • Cessnock City Council Operational Budget

Location

Booth Park, Kurri Kurri 2327  View Map

Google Map