Anderson Avenue, Paxton – Walking Path - STAGE 2

  • Project typeWalking Pathway Construction
  • Project value$580,000
  • Project scheduleJuly 2025–October 2025
  • Completion Date19 September 2025

Anderson Avenue, Paxton - Walking Path

Stage 1 - Completed 19 September 2025

Stage 2 - Estimated completion by end of March 2026


Background

Anderson Avenue, Paxton received $580,000 under the ‘Active Transport to School - Get Active NSW’ Grant funded by Transport for NSW, to construct a pathway which will encourage children to safely walk and ride to school.


Scope of Works

The walking path at Anderson Avenue, Paxton includes:

  • 1.8m wide walking pathway
  • 90m in length from the corner of Paxton Public School to the corner of McDonald Ave and Anderson Avenue
  • Removal of guardrail
  • Completion of kerb and gutter to Paxton Public School
  • Connection to Paxton Park

Location

Map.png

Traffic Management

Traffic control and reduced speed limits will be in place for the duration of the works to ensure resident and pedestrian safety. This may cause minor traffic delays along portions of Anderson Avenue.

There will also be restricted access for pedestrians and bicycle riders along the northern side of Anderson Avenue. Access and parking restrictions will be in place adjacent to the work site.

Residents will be notified for how this project will impact their everyday use of this road whilst construction works are ongoing. 


Funding

The project budget has been entirely funded by the ‘Active Transport to School - Get Active NSW’ Grant which has been endorsed by Transport for NSW.