Yango Creek Road Bridge
- Project typeBridge replacement
- Project value$1,403,000
- Project scheduleDesign completion June 2022; Construction July 2022 to May 2023.
- Completion Date16 May 2023
Background
Council has completed the replacement of Yango Creek Road Bridge at Wollombi. It provides an essential point of access for residents, visitors and tourists and is heavily relied on by local business for the transportation of cattle and equine, and for viticulture and agriculture operations.
The old bridge was constructed of ageing timber beams and had a reduced load limit. In addition, it was overtopped during flood events which isolated the community. The final design of the new bridge includes an open load limit, a pedestrian path and have a lifespan of over 75 years.
This project forms part of Council's Operational Plan. You can find it within the Operational Plan with the Project ID CBS 2017 004.
Location
Scope of works
The old bridge was replaced with a new concrete 2 lane bridge on approximately the same alignment and level as the old bridge.
Features of the works include:
- New road approaches
- Fencing
- Drainage
- Erosion and sediment control
- Retaining structure
- Pavements and pavement markings
- Landscaping
- Signage and lighting
Funding
Council secured Federal Government funding in 2020 under the Bridges Renewal Program as well as the NSW Government’s Disaster Relief Funding for the replacement of the bridge and the road approaches.
Completion