Due to a fire at Cleanaway’s processing facility in Sydney, Cessnock Community Recycling Centre (CRC) has now reached full capacity and will be unable to accept certain problem waste items until servicing resumes.
This project formed part of Council's Shared Pathway Program.
The scope of works for the Millfield path construction project includes all works necessary to construct a concrete path 670 metres in length and 2.5 metres wide between Millfield Road and Wollombi Road via Crawfordville Park. The scope of works also includes construction of a pedestrian refuge on Millfield Road and box culvert structure with land reclamation in Crawford Avenue.
The works commenced in February 2023 and were completed August 2023.
The planned works were between Millfield Road and Wollombi Road, via Crawfordville Park.